Saturday, March 28, 2009

Week 13 - Finished walls and kitchen cabinets

The walls were finished off super smooth this week and the house is beginning to look like a home at last. The kitchen and bathroom cabinets started to go in on Friday and the wood looks rich and gorgeous. We chose a Eucalyptus hybrid wood for the cabinets which is a sustanable fast growing hard wood and with the cherry stain it looks fantastic.


Kitchen cabinets


Kitchen cabinets going up


Smooth walls in the sun room - the light and architectural shapes look fantastic in there


The shower areas had the backing added ready for the tiling


The living room with finished walls (we have selected the tiles to cover the brick fireplace)

Friday, March 20, 2009

Week 12 - Sheetrock, solar panels and new window

The sheetrock is up and so we have rooms! For the rest of the week the team has been taping and filling the cracks in the sheetrock in order for us to have smooth rather than textured walls.


The sheetrock has been taped in the kitchen


Sheetrock in the sunroom

Also this week we had the solar panels installed! These will be generating 110% of our electricity needs which will cover our energy usage for a number of years to come.


Solar panels on the roof


Solar inverter panel where all the magic happens to feed excess power back to the grid

We had the final window installed in the master bathroom. Together with the sun tube there is a nice lot of light in there now.


New window in the master bathroom. You can also see the smooth walls in there.

Monday, March 16, 2009

Sheetrock

The sheetrock team worked over the weekend and finished on Monday. They have transformed the place!


Living room

Master bedroom


Master bathroom


Guest bathroom


Friday, March 13, 2009

Week 11 - Finishing electrical and inspections

Not much change this week. It was a big week for inspections:
  • Electrical: passed
  • Sheer in sunroom: passed
  • Insulation in sunroom: passed

Saturday, March 7, 2009

Week 10 - Patio doors, insulation and walls

The patio doors and the big tub went in this week! The insulation and walls started to go up too.

The new patio doors are in! You can see here the walls starting to go up - sheetrock next!

We are getting the house well insulated and sealed tight to maximize energy efficiency


Although many said it couldn't be done...the tub does fit in the bathroom and is plumbed in!